Project charter template

A project charter is the short document that gets a project agreed before work starts: why it exists, how success will be measured, what is in and out of scope, the milestones, who does what, the assumptions and risks, and who approved it. This builder turns those answers into a numbered charter with milestone and roles tables and an approval block. Copy one of the five worked examples below, or enter your project and download it as Word or PDF.

Version
1.0.0
Reviewed
2026-11-23
Reviewer
TemplateNook editorial reviewCharter structure, scope and success-criteria wording, milestone and roles tables, date ordering, approval handling, and export parity. No contract, procurement, legal or financial-approval review.
Problem, objective and success criteria
Scope in and out, side by side
Milestone and roles tables
Approval block for the sponsor

Fill in the project charter builder

Enter the sponsor, project manager and dates, then the problem and the measurable success criteria. Scope goes in as two lists, in and out; milestones and roles go in as structured lines and come out as real tables. Assumptions, risks and an optional resource summary follow, and the approval block records who approved the charter and when. A charter that is not yet approved stays marked as a draft.

Guided draft builder

Enter verified details

* marks fields required for final exports. Blank fields remain visible as placeholders in draft preview.

Reusable sender profile

Enter your company, name, email, or address once to auto-fill across templates. Stays in this browser.

An internal planning estimate, not a quote, purchase order or budget approval.

Same values in every output

Draft preview

Draft · fields missing

Draft — review required

Project charter: [Project title]

[Organization or department] · Project charter

Sponsor
[Project sponsor]
Project manager
[Project manager]
Status
[Approval status]
Target start
[Target start date]
Target end
[Target end date]
Template version
1.0.0

1. Problem and objective

[Problem statement and business objective]

2. Success criteria

  • [Measurable success criteria]

3. Scope

In scope

  • [In scope]

Out of scope

  • [Out of scope]

4. Milestones

MilestoneTarget dateOwner
[Milestone][Target date][Owner]

5. Roles and responsibilities

RolePersonResponsibility
[Role][Person][Responsibility]

6. Assumptions and constraints

  • [Assumptions and constraints]

7. Initial risks

  • [Initial risks]

8. Approval

Approved byDate approvedSignature
[Sponsor: [Project sponsor], on approval]

Review, copy, or export

Copy is an honest paste workflow. Word, PDF, and Excel downloads are real files built after server-side validation.

No account required

Before final export

  • Complete every required field and correct highlighted errors.
  • Leave labelled example mode before downloading.
  • Personally verify facts, dates, owners, and scope.

Editorial examples

Five project charter examples

Five projects with invented organizations, people and dates. Each shows the lines that carry the charter. Milestones and roles are written the way the builder reads them.

  1. 01

    Product feature launch

    Use when: A product team proposing a new feature with a clear business case and launch date.

    Self-service returns portal · Sponsor: Priya Shah (operations director) · Project manager: Morgan Ellis · 11 January to 30 April 2027

    Problem: returns can only be started by email, taking three emails and two days on average and a third of support’s time

    Success: 70% of returns started without contacting support by 30 June 2027; support time on returns down by half

    In scope: returns page for orders delivered in the last 30 days; printable label; email confirmations

    Out of scope: exchanges (phase two); marketplace sellers’ items; refund policy changes

    Milestone: Launch to all customers | 30 Apr 2027 | Morgan Ellis

    Role: Sponsor | Priya Shah | Approves scope changes and clears blockers

    What to change: Exchanges are the obvious next request. Putting them out of scope, with a note that they are phase two, keeps the launch date safe.

  2. 02

    Agile team charter

    Use when: A new delivery team agreeing its mission, measures and ways of working rather than a fixed scope.

    Checkout team charter · Sponsor: Jordan Blake (head of product) · Team lead: Sam Rivera · January to June 2027

    Problem: one in five shoppers abandon checkout on mobile, and no team owns the checkout end to end

    Success: mobile checkout completion up from 80% to 88% by 30 June 2027; no release rolled back for checkout defects

    In scope: the mobile and desktop checkout, payment page and order confirmation

    Out of scope: the product pages, search and the loyalty scheme

    Milestone: First improvement released | 5 Feb 2027 | Sam Rivera

    Assumption: the team keeps the same five people for the six months

    What to change: An agile charter fixes the mission and the measures and lets the backlog change. Review the charter at each quarterly planning session rather than every sprint.

  3. 03

    Internal workflow automation

    Use when: An internal team automating a manual process, with no customer-facing change.

    Automated invoice matching · Sponsor: Alex Kim (finance director) · Project manager: Jo Park · 1 February to 31 May 2027

    Problem: the finance team matches 1,200 supplier invoices to purchase orders by hand each month

    Success: 80% of invoices matched automatically by 31 May 2027; month-end close two days shorter

    Out of scope: changes to the approval limits; supplier onboarding

    Role: Process owner | Jo Park | Defines the matching rules and signs off testing

    Risk: Supplier invoice formats vary: start with the top 20 suppliers, who send 70% of invoices

    What to change: For internal projects, name a process owner as well as the project manager. They own the process after the project closes.

  4. 04

    Client portal rollout

    Use when: A service business moving client document exchange from email to a portal.

    Client document portal · Sponsor: Rae Whitcombe (managing partner) · Project manager: Devon Hale · 15 February to 30 June 2027

    Problem: client documents arrive by email and are saved in different places, so files are hard to find at year end

    Success: 90% of active clients using the portal by 30 June 2027; no client documents received by email after 1 July

    In scope: portal set-up, client invitations, staff training, a guide for clients

    Out of scope: moving historic files; changes to engagement letters

    Assumption: the portal supplier’s data-protection terms are approved by 1 March

    What to change: Where the project depends on a supplier’s terms, make approval an assumption with a date. If it slips, the charter shows the start date is at risk.

  5. 05

    IT or office migration

    Use when: Moving offices, systems or devices, where the date is fixed and disruption must be limited.

    Office move and network upgrade · Sponsor: Priya Raman (managing director) · Project manager: Chris Varga · 4 January to 26 March 2027

    Problem: the current lease ends on 31 March and the new office has no network installed

    Success: all 45 staff working from the new office on 29 March 2027 with no more than half a day of downtime

    Milestone: Network installed and tested | 12 Mar 2027 | Chris Varga

    Milestone: Move weekend | 27 Mar 2027 | Chris Varga

    Risk: Internet line installation date slips: order now and book a mobile backup

    What to change: When the end date is fixed by a lease or contract, say so in the problem statement. Every other trade-off is made around that date.

These examples are written illustrations, not records of real customers, invoices or clients. To produce a version with your own verified details — and a real Word or PDF file rather than a copied block of text — use the builder above.

Field coverage

What a project charter should include

The builder above requires the items marked with an asterisk before it will produce a final file. This list is the reasoning behind that field model.

  • The project title, organization, sponsor and project manager.
  • A problem statement: what is wrong or missing today, and who it affects.
  • Success criteria you can measure, each with a number, a date or both.
  • What is in scope, and just as clearly, what is out of scope.
  • The key milestones with a target date and an owner.
  • The core roles: who sponsors, who manages, who delivers and who signs off.
  • Assumptions and constraints the plan depends on, and the initial risks with a response.
  • An approval block recording who approved the charter and when.

Method

How to write a project charter

  1. 01

    Start with the problem, not the solution

    Describe what is going wrong or what is missing, and who it affects. A charter that starts with “build a portal” has skipped the question of whether a portal is the answer.

  2. 02

    Make every success criterion measurable

    “Improve the returns process” cannot be checked. “70% of returns started without contacting support by 30 June” can. If you cannot measure it, you will not be able to say the project worked.

  3. 03

    Write the out-of-scope list

    Most scope arguments are about things nobody wrote down. Listing what the project will not do, such as exchanges or a policy change, settles them before they start.

  4. 04

    Put milestones and roles in tables

    Write milestones as Milestone | Target date | Owner and roles as Role | Person | Responsibility. The builder lays them out as tables so gaps, such as a milestone with no owner, are obvious.

  5. 05

    Name the assumptions you are relying on

    An assumption that turns out false is a risk you did not record. Write down what must be true for the plan to work, and who will confirm it.

  6. 06

    Get the sponsor’s approval and record it

    Share the charter as a draft, collect comments, then record who approved it and when. An unapproved charter stays marked as a draft in every export.

Where project charters go wrong

  • Success criteria with no number or date, so the project can never be judged.
  • No out-of-scope list, so every new request becomes part of the project.
  • A sponsor named who has not agreed to sponsor it.
  • Milestones with no owner, or dates copied from a wish rather than a plan.
  • Treating the charter as a contract with a client or a supplier.
  • A charter that is never updated when scope or dates formally change.
  • Writing ten pages when two would get read and approved.

Questions

Project charter questions

Answers from the same editorial review that owns the builder. Where a question touches legal, tax or regulatory ground, the answer says so rather than guessing.

Report a correction

What is a project charter?

A short document, usually one or two pages, that sets out why a project exists, what it will deliver, how success is measured, what is out of scope, the milestones, who is involved and who approved it. It is agreed before the work starts and gives the project manager the authority to proceed.

What should a project charter include?

The problem and objective, measurable success criteria, scope in and out, key milestones with owners, core roles, assumptions and constraints, initial risks, an optional resource and budget summary, and an approval block with who approved it and when.

What is the difference between a project charter and a project plan?

The charter agrees the why, the what and the who at a high level, and is approved by the sponsor. The project plan is the detailed how: tasks, schedules, dependencies and resources. Write the charter first; the plan follows from it.

Who approves a project charter?

The project sponsor, the person who owns the business case and can make decisions about scope, time and money. Some organizations also need a steering group or budget holder; record whoever your own process requires. The builder keeps the charter marked as a draft until approval details are entered.

Is a project charter a contract?

No. A charter is an internal alignment document. Work for a client is agreed in a contract or statement of work, purchases in a purchase order, and budgets through your finance process. The charter can refer to them but does not replace them.

What is a project brief, and how is it different from a charter?

Many teams use “project brief” for the same thing, or for a lighter version written before a charter. If your organization uses briefs, this builder works for them too: fill the problem, success criteria and scope, keep the other sections short, and leave the status as Draft until it is agreed.

Can I use this charter template in Word or Google Docs?

Yes. Download the charter as a Word file, which opens in Word and in Google Docs, or as a PDF for sign-off, or copy it straight into a Google Doc.

Editorial and review record

What changed in version 1.0.0

First release: a project charter builder with the problem and objective, measurable success criteria, scope in and out, milestone and roles tables built from structured lines, assumptions and constraints, initial risks, an optional resource summary and an approval block, plus five worked examples and reviewed answers. Charters that are not approved stay marked as drafts.

Scope boundary

A project charter is an internal alignment document. It is not a binding client contract, statement of work, purchase order or budget approval; agree those through your own contracting and finance process. Approval here records who agreed the charter, nothing more.

Sources used

Sources inform field coverage and conservative boundaries. They do not certify the generated document or endorse TemplateNook.

Read the full review and export method

Adjacent jobs

Other reviewed workflows

Project reporting

Reviewed

v1.0.0 · reviewed 2026-11-23

Project status report

Report a project’s overall Red, Amber or Green status, what was done, what comes next, milestones, risks and the decisions you need, in one page people will actually read.

Word (.docx)PDF (.pdf)
Open workflow

Client operations

Reviewed

v1.0.0 · reviewed 2026-11-23

Client intake form

Collect a new client’s contacts, billing instructions, goals, scope, systems, stakeholders and kickoff plan in one business intake form, without passwords or sensitive personal data.

Word (.docx)PDF (.pdf)